首页土木建筑建筑经济学工程管理专业英语 12 Unit Twelve Schedule Control(1).pptx

12 Unit Twelve Schedule Control(1).pptx

页数:14页文件大小:93.0 KB来源: 工程管理专业英语ppt课件

本课件为《工程管理专业英语》Unit Twelve 进度控制(1)(Schedule Control (1))单元教学内容,含词汇短语与问答两部分,先列出本单元核心术语的英汉对照释义,再以英文问答复述项目控制过程与报告期、基准计划与变更处理等要点,适用于专业英语阅读与翻译训练。

进度控制(1)单元词汇章节标题页,标示 Vocabulary, Phrases and Expressions 词汇与短语部分开始
进度控制(1)单元词汇页,收录项目控制过程、项目范围、基准计划等英汉术语对照与释义
进度控制(1)单元词汇页,收录偏差、实际完成时间、总时差等英汉术语对照与释义
查看本课件的文字版(共 14 页,供检索与复制)

第1页:Unit Twelve 词汇与短语

Vocabulary, Phrases and Expressions(词汇与短语)

本页为 Unit Twelve Schedule Control (1)(进度控制(1))单元的词汇部分标题页,其后各页按词条列出本单元核心术语的英文表达与中文释义。

第2页:项目控制过程与基准计划

项目控制过程与基准计划:Unit Twelve Schedule Control (1)(进度控制(1))单元词汇与短语,下列词条给出英文术语与中文释义。

project control process
项目控制过程
project scope
项目范围
baseline plan
基准计划
project team
项目团队
reporting period
报告期
data on actual performance
实际执行中的数据

第3页:偏差分析与项目变更词汇

偏差分析与项目变更词汇:Unit Twelve Schedule Control (1)(进度控制(1))单元词汇与短语,下列词条给出英文术语与中文释义。

variances
偏差;不一致
actual finish times
实际完成时间
total slack
总时差
project changes
项目变更

第4页:项目控制过程的内容

1. What are involved in the project control process?

The project control process involves regularly gathering data on project performance, comparing actual performance to planned performance, and taking corrective actions if actual performance is behind planned performance.

第5页:定期报告期的建立

2. How to establish a regular project reporting period?

Reporting may be daily, weekly, bi-weekly, or monthly, depending on the complexity or overall duration of the project.

第6页:报告期应收集的数据

3. During each reporting period, which kinds of data or information to be collected?

  • Data on actual performance. This includes
  • the actual time that activities were started and/or finished
  • the actual costs expended and committed
  • Information on any changes to the project scope, schedule, and budget.

第7页:新基准计划的建立条件

4. On what condition must a new baseline be established?

Once changes are incorporated into the plan and agreed on by the customer, a new baseline plan has to be established.

第8页:项目严重失控的应对

5. If a project gets too far out of control, what’s the wise method to solve that problem?

It is wise to increase the frequency of reporting until the project is back on track.

第9页:实际完成时间与时差计算

6. What will determine the earliest start and earliest finish times for the remaining activities in the network diagram, as well as the total slack?

The actual finish times (AF) of completed activities will.

第10页:影响进度的变更来源

7. What might initiate the changes that have an impact on the schedule?

These changes might be initiated by the customer or the project team, or they might be the result ofan unanticipated occurrence.

第11页:变更提出时点的影响

8. The degree of impact may depend on when the changes are request, why?

If they’re requested early in the project, they may have less impact on cost and schedule than if they’re requested later in the project.

第12页:变更影响的评估与批准

9. When the customer request a change, who should estimate the impact on the project budget and schedule and obtain custom approval before proceeding?

the contractor or project team

第13页:变更对进度的影响

10. With respect to the project schedule, what result can changes bring?

Changes can result in the addition or deletion of activities, the resequencing of activities, the changing of activities’ duration estimates or a new required completion time for the project.

第14页:Unit Twelve 单元结束页

End of This Unit(本单元结束)

本页为 Unit Twelve Schedule Control (1)(进度控制(1))单元的结束页,标示本单元的词汇与问答内容到此结束。