页数:16页文件大小:97.5 KB来源: 工程管理专业英语ppt课件
本课件为《工程管理专业英语》Unit Thirteen 进度控制(2)(Schedule Control (2))单元教学内容,含词汇短语与问答两部分,先列出本单元核心术语的英汉对照释义,再以英文问答复述进度更新的计算方法、负时差路径的加速策略等要点,适用于专业英语阅读与翻译训练。
Vocabulary, Phrases and Expressions(词汇与短语)
本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的词汇部分标题页,其后各页按词条列出本单元核心术语的英文表达与中文释义。
网络计划与甘特图工具词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。
进度控制与纠正措施词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。
生产率与奖惩条款词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。
Questions and Answers(问题与解答)
本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的问答部分标题页,其后各页以英文问答形式复述本单元要点。
1. How to calculate an updated project schedule once data have been collected on the actual finish time of completed activities and the effects of any project changes?
These calculations are based on the methodology:
2. Schedule control involves four steps, what are they?
(1) Analyzing the schedule to determine which areas may need corrective action;(2) Deciding what specific corrective actions should be taken;(3) Revising the plan to incorporate the chosen corrective actions;(4) Recalculating the schedule to evaluate the effects of the planned corrective actions.
3. What paths must be applied a concentrated effort to accelerate project progress?
the paths with negative slack.
4. When analyzing a path of activities that have negative slack, which kinds of activities should be focused on?
(1) Activities that are near term (that is, in progress or to be started in the immediate future).(2) Activities that have long duration estimates.
5. What is the obvious way to reducing the duration estimates of activities?
The obvious way is to apply more resources to speedup an activity.
6. What are the other ways to reducing the duration estimates of activities?
7. What is the key to effective schedule control?
The key to effective schedule control is to aggressively address any paths with negative or deteriorating slack values as soon as they are identified, rather than hoping that things will improve as the project goes on.
8. On projects that don’t have negative slack, what’s important to do?
On projects that don’t have negative slack, it’s important not to let the slack deteriorate by accepting delays and slippages.
9. What can push an information system project beyond its originally scheduled?
Numerous unexpected circumstances arise that can push an IS development project beyond its originally scheduled due date.
10. What are the changes that commonly become necessary during information system development project?
Changes to input screens; Changes to reports; Changes to on-line queries; Changes to database structures; Changes to software processing routines; Changes to processing speeds; Changes to storage capacities; Changes to business processes; Changes to software resulting from hardware upgrades or, conversely, hardware upgrades resulting from the availability of more powerful software
End of This Unit(本单元结束)
本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的结束页,标示本单元的词汇与问答内容到此结束。
下载地址:{{downurl}}
{{{a}}}
{{#b}}{{{b}}}
{{/b}} {{/title}} {{#nolog}}登陆注册
{{/nolog}} {{#djsx}}点我刷新
{{/djsx}} {{#gocz}} {{/gocz}} {{#ffqr}} {{/ffqr}}