第1页:Unit Thirteen 词汇与短语

Vocabulary, Phrases and Expressions(词汇与短语)

本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的词汇部分标题页,其后各页按词条列出本单元核心术语的英文表达与中文释义。

第2页:网络计划与甘特图工具词汇

网络计划与甘特图工具词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。

network-based planning
基于网络的计划
Gantt chart
甘特图
software packages
软件包
completed activities
已完成活动
database
数据库
supplier
供应商

第3页:进度控制与纠正措施词汇

进度控制与纠正措施词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。

preliminary review
初步评审
schedule control
进度控制
corrective action
纠正措施
negative slack
负时差
positive slack
正时差
top priority
最高优先级

第4页:生产率与奖惩条款词汇

生产率与奖惩条款词汇:Unit Thirteen Schedule Control (2)(进度控制(2))单元词汇与短语,下列词条给出英文术语与中文释义。

productivity
生产率
a bonus provision
奖励条款
a penalty provision
惩罚条款
information system
信息系统

第5页:Unit Thirteen 问题与解答

Questions and Answers(问题与解答)

本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的问答部分标题页,其后各页以英文问答形式复述本单元要点。

第6页:进度更新的计算方法

1. How to calculate an updated project schedule once data have been collected on the actual finish time of completed activities and the effects of any project changes?

These calculations are based on the methodology:

  • The earliest start and finish times for the remaining, uncompleted activities are calculated by working forward through the network, but they’re based on the actual finish times of completed activities and the estimated durations of the uncompleted activities.
  • The latest start and finish times for the uncompleted activities are calculated by working backward through the network.

第7页:进度控制的四个步骤

2. Schedule control involves four steps, what are they?

(1) Analyzing the schedule to determine which areas may need corrective action;(2) Deciding what specific corrective actions should be taken;(3) Revising the plan to incorporate the chosen corrective actions;(4) Recalculating the schedule to evaluate the effects of the planned corrective actions.

第8页:需重点加速的负时差路径

3. What paths must be applied a concentrated effort to accelerate project progress?

the paths with negative slack.

第9页:负时差路径的重点工作

4. When analyzing a path of activities that have negative slack, which kinds of activities should be focused on?

(1) Activities that are near term (that is, in progress or to be started in the immediate future).(2) Activities that have long duration estimates.

第10页:缩短工期的直观方法

5. What is the obvious way to reducing the duration estimates of activities?

The obvious way is to apply more resources to speedup an activity.

第11页:缩短工期的其他方法

6. What are the other ways to reducing the duration estimates of activities?

  • Reducing the scope or requirements for an activity is another way to reduce its duration estimate.
  • Increasing productivity through improved methods or technology is yet another approach to reducing activities’ durations.

第12页:有效进度控制的关键

7. What is the key to effective schedule control?

The key to effective schedule control is to aggressively address any paths with negative or deteriorating slack values as soon as they are identified, rather than hoping that things will improve as the project goes on.

第13页:无负时差项目的注意点

8. On projects that don’t have negative slack, what’s important to do?

On projects that don’t have negative slack, it’s important not to let the slack deteriorate by accepting delays and slippages.

第14页:信息系统项目超期的原因

9. What can push an information system project beyond its originally scheduled?

Numerous unexpected circumstances arise that can push an IS development project beyond its originally scheduled due date.

第15页:信息系统开发中的常见变更

10. What are the changes that commonly become necessary during information system development project?

Changes to input screens; Changes to reports; Changes to on-line queries; Changes to database structures; Changes to software processing routines; Changes to processing speeds; Changes to storage capacities; Changes to business processes; Changes to software resulting from hardware upgrades or, conversely, hardware upgrades resulting from the availability of more powerful software

第16页:Unit Thirteen 单元结束页

End of This Unit(本单元结束)

本页为 Unit Thirteen Schedule Control (2)(进度控制(2))单元的结束页,标示本单元的词汇与问答内容到此结束。