本课件为《工程管理专业英语》Unit Five 项目预算(2)(The Project Budget (2))单元教学内容,含词汇短语与问答两部分,先列出本单元核心术语的英汉对照释义,再以英文问答复述沉没成本与预计总成本、完工进度与成本偏差监控等要点,适用于专业英语阅读与翻译训练。

项目预算(2)单元词汇章节标题页,标示 Vocabulary, Phrases and Expressions 词汇与短语部分开始
项目预算(2)单元词汇页,收录财务计算、沉没成本、工作成本预测等英汉术语对照与释义
项目预算(2)单元词汇页,收录工作状况报告、完工劳动单元、里程碑累计等英汉术语对照与释义
查看本课件的文字版(共 15 页,供检索与复制)

第1页:Unit Five 词汇与短语

Vocabulary, Phrases and Expressions(词汇与短语)

本页为 Unit Five The Project Budget (2)(项目预算(2))单元的词汇部分标题页,其后各页按词条列出本单元核心术语的英文表达与中文释义。

第2页:成本核算与项目控制词汇

成本核算与项目控制词汇:Unit Five The Project Budget (2)(项目预算(2))单元词汇与短语,下列词条给出英文术语与中文释义。

financial accounting
财务计算;财务会计
sunk cost
沉没成本;已支付成本
forecasting for activity cost
工作成本预测
cost to date
完工成本
cost committed
承诺成本
cost exposure
附加成本
project control
项目控制

第3页:完工进度与成本预测词汇

完工进度与成本预测词汇:Unit Five The Project Budget (2)(项目预算(2))单元词汇与短语,下列词条给出英文术语与中文释义。

job status report
工作状况报告
units of work completed
完工劳动单元
incremental milestones
里程碑累计
field observations
现场观察
cost ratio
成本率
estimated total cost for completion
预计完工总成本

第4页:Unit Five 问题与解答

Questions and Answers(问题与解答)

本页为 Unit Five The Project Budget (2)(项目预算(2))单元的问答部分标题页,其后各页以英文问答形式复述本单元要点。

第5页:传统财务会计的不足

1. What’s the disadvantage of traditional financial accounting schemes?

Traditional financial accounting schemes are not adequate to reflect the dynamic nature of a project

第6页:沉没成本的含义

2. What does the term“sunk costs”mean?

Generally, past expenditures represent sunk costs that cannot be altered in the future and may or may not be relevant in the future.

第7页:预计总成本的计算

3. How to calculate the estimated total cost?

Estimated total costs are the sum of cost to date, commitments and exposure.

第8页:偏差账户为何重点关注

4. For project control, managers would focus particular attention on items indicating substantial deviation from budgeted accounts, why?

If substantial deviations continue to accumulate, then the cost-to-complete will be even higher.

第9页:成本超支的诱因

本页承接上一页问答内容,继续给出英文说明。

5. which factors may cause overruns in cost? Overruns in cost might be due to lower than expected productivity, higher than expected wage rates, higher than expected material costs, or other factors.

第10页:预测总成本的两种方法

6. How many methods can be used to get the forecast total cost? What are they?

  • Algebraically, a linear estimation formula is generally one of two forms.
  • Using a linear extrapolation of costs to forecast total cost.
  • Alternatively, the use of measured unit cost amounts can be used for forecasting total cost.

第11页:完工劳动单元的含义

7. What does the term“units of work completed”mean?

“Unit of work completed” means the proportion of completed work amounts.

第12页:增量里程碑的理解

8. How to understand the term“incremental milestone”?

Particular activities can be sub-divided or"decomposed" into a series of milestones, and the milestones can be used to indicate the percentage of work complete based on historical averages.

第13页:成本率的计算

9. How to calculate cost ratio?

The cost ratio would be the result as the cost incurred at a particular date divided by the budget.

第14页:工作成果的自动数据采集

10. In some cases, automated data acquisition for work accomplishments might be instituted, why?

These measurements of actual progress should be stored in a central database and then processed for updating the project schedule.

第15页:Unit Five 单元结束页

End of This Unit(本单元结束)

本页为 Unit Five The Project Budget (2)(项目预算(2))单元的结束页,标示本单元的词汇与问答内容到此结束。